Review and Post the Reallocation Journal
3 minute read
The journal lines that a run creates are ordinary project journal lines. You review them in the Project Journals page and post them with the standard Post action. Until you post, you stay in control: you can check the numbers, correct a share, or delete the run and start over.
To open the journal for a run
Do one of the following:
- After a run, choose Yes when the app asks if you want to open the journal.
- Choose the 🔎 icon, enter Reallocation Runs, and then choose the related link. Select the run, and then choose Open Journal.
The journal opens on the run’s batch, filtered to the lines of that run.
Review the lines
The following fields on the journal lines show where a line came from. You can add them to the page with Personalize if they are not shown.
Reallocation Run No.- The run that created the line. Blank on lines that you entered yourself.Reallocation Line Type-Destinationfor a line that brings cost to a project, orSource Reversalfor a line that moves cost off a source project.Reallocation System Amount- The amount that the run calculated for the line.Reallocation Adjusted- Selected when someone changed the quantity or cost on the line after the run created it.
Adjust a destination line
You can change the quantity or cost on a destination line, for example to move part of a share from one project to another. When the total cost of a line changes, the Reallocation Adjusted field is selected. The Reallocation System Amount keeps the amount that the run calculated, so you can always see the original value.
You can also change the No. field to post a line to a different G/L account. The quantity and cost on the line are kept.
Note
Source reversal lines cannot be changed or deleted. To remove them, delete the run.To post the journal
- In the Project Journals page, check the lines.
- Choose Post.
Before anything is posted, the app checks every run in the batch. The destination lines of a run must add up exactly to the amount the run needs to allocate:
- For a G/L account source, the destination lines must add up to the run’s
Source Total Amount. - For a project source, the destination lines must add up to the total of the source reversal lines.
If a run does not add up, for example because you changed or deleted a destination line, posting stops before any line in the batch is posted. The message names the run, the current total and the amount it must add up to. Adjust the destination lines and post again.
Example
A run allocates 10,000.00 to projects A (7,500.00) and B (2,500.00). You agree with the project manager to move 500.00 from A to B. Change the cost on line A to 7,000.00 and on line B to 3,000.00. Both lines are marked as adjusted, the total is still 10,000.00, and the batch posts.Result
- The app creates Project Ledger Entries for the lines, through the standard project journal posting.
- Each project ledger entry keeps the run number, the line type, the calculated amount and the adjusted flag from its journal line. For more information, see Trace an Allocation Back to its Source.
- When all of a run’s lines are posted, the run status changes from
OpentoPosted.