This the multi-page printable view of this section. Click here to print.

Return to the regular view of this page.

Pryme Cost Reallocation

Learn to use Pryme Cost Reallocation by browsing documentation and walkthroughs.

Pryme Cost Reallocation helps you move costs to the projects that consumed them. Shared costs, such as rent, IT, insurance or the cost of a shared service project, often land on a general ledger account or on a single overhead project. Cost Reallocation spreads those costs across your delivery projects in a repeatable, controlled way, so that every project carries its fair share and your project margins tell the truth.

You define the rules once. Each period, you run a rule for a date range, and the app calculates each project’s share and writes the result to a Project Journal as ordinary journal lines. You review the lines, adjust them if you need to, and post them with the standard project journal posting. Nothing is posted behind your back.

Every posted entry keeps a link to the run and the rule that produced it, so you, your auditors and your project managers can always answer the question where did this cost come from?


Key concepts

  • Reallocation rule - Describes what to reallocate and where to. A rule holds a source (G/L accounts or projects), a set of destination projects, an allocation method, and the project tasks, G/L accounts and line types for the generated journal lines.
  • Source - Where the cost to reallocate comes from:
    • G/L Account - The net amount posted to one or more G/L accounts in the period.
    • Project - The usage cost posted to one or more overhead or shared service projects in the period. The cost is moved off the source projects with a reversing entry.
  • Destination projects - The projects that receive a share of the cost.
  • Allocation method - How each destination project’s share is calculated:
    • Cost Based - In proportion to each project’s own usage cost in the period.
    • Hours Based - In proportion to the resource hours posted to each project in the period.
  • Reallocation run - One execution of a rule for one period. A run records the period, the source total and the journal batch, and tracks whether its journal lines are Open or Posted.
  • Reallocation trace - The link from each posted Project Ledger Entry back to the run and rule that created it.

How it works

StepWhat you doWhat the app does
1Set up project tasks, G/L accounts and a journal batch.-
2Create a reallocation rule.Validates the G/L accounts and journal batch.
3Run the rule for a period.Calculates the source total and each project’s share, and creates journal lines.
4Review and adjust the journal.Flags lines you changed, and blocks posting if the lines no longer add up.
5Post the journal.Posts project ledger entries, stamps the trace, and marks the run as Posted.
6Trace a posted entry.Shows the run, rule and calculated amount behind every entry.

Setup and configuration

Learn what to set up before you create your first reallocation rule.

Reallocate Costs

Learn how to create reallocation rules, run them for a period, and review and post the results.

Trace Reallocated Costs

Learn how to trace a posted project entry back to the run and rule that created it.

Release Notes

See what is new in each version of Pryme Cost Reallocation.

1 - Setup and configuration

Learn what to set up before you create your first reallocation rule.

Pryme Cost Reallocation has no setup page of its own. It uses standard Business Central projects, project tasks, G/L accounts and project journals. Before you create your first reallocation rule, make sure the following is in place.

Permissions

The app comes with two permission sets. Assign them on the Users or Permission Sets page.

  • Cost Reallocation - Read - View reallocation rules, reallocation runs and the reallocation trace.
  • Cost Reallocation - Edit - Create, change and delete reallocation rules, run rules, and delete open runs. Includes Cost Reallocation - Read.

Users who review and post the generated journal lines also need the standard permissions for project journals and project posting.

Project journal template and batch

Every run writes its journal lines to a project journal batch. We recommend that you create a dedicated batch for reallocations, so that reallocation lines are not mixed with other project journal lines.

  1. Choose the ๐Ÿ”Ž icon, enter Project Journals, and then choose the related link.
  2. In the Batch Name field, open the list of batches and create a new batch, for example REALLOC.
  3. In the No. Series field, select a number series.

When the batch has a No. Series, all lines from one run share one document number from that series. When the batch has no No. Series, the lines keep the standard default document number.

Project tasks

The generated lines are posted to a specific project task.

  • On every destination project, create the project task that receives the allocated cost, for example OVERHEAD. The task must have the Project Task Type set to Posting.
  • If you reallocate from projects, create the task that receives the reversing entry on every source project as well, for example REALLOC-OUT. This task must also be a Posting task.

Use the same task number on all projects that a rule covers. The rule holds one task number for all destination projects and one for all source projects.

G/L accounts

The generated journal lines have the type G/L Account. Decide which accounts to use:

  • A destination G/L account for the allocated cost on the destination projects. The account must have Account Type set to Posting, must not be blocked, and must have Direct Posting selected.
  • A reversal G/L account for the reversing entry on the source projects. You need this only when you reallocate from projects.

You set the project tasks, G/L accounts and journal batch for each rule on the rule itself. For more information, see Create Reallocation Rules.

2 - Reallocate Costs

Learn how to create reallocation rules, run them for a period, and review and post the results.

Many costs cannot be posted directly to the project that caused them. Office rent, software licences, a shared engineering team or a central project management office are paid centrally, but they are part of the real cost of delivering each project. If those costs stay on a G/L account or on an overhead project, your project margins look better than they are, and project pricing is based on incomplete numbers.

Cost reallocation is a period-end task. For each period, you take the shared cost, split it across the projects that benefited from it, and post each project’s share to that project. Pryme Cost Reallocation turns this into a repeatable routine: you describe the split once as a rule, and run the rule every period.

The following table describes a sequence of tasks, with links to the topics that describe them.

ToSee
Define what to reallocate, to which projects, and how.Create Reallocation Rules
Choose between a G/L account source and a project source.Reallocation Sources
Choose how the cost is split between projects.Allocation Methods
Run a rule for a period and generate journal lines.Run a Reallocation Rule
Check, adjust and post the generated lines.Review and Post the Reallocation Journal
Follow up on runs, or undo a run that is not posted yet.Manage Reallocation Runs

Create Reallocation Rules

Learn how to create a rule that describes the source, the destination projects and the allocation method.

Reallocation Sources

Learn how to reallocate costs from G/L accounts or from other projects.

Allocation Methods

Learn how the cost-based and hours-based methods split the cost between projects.

Run a Reallocation Rule

Learn how to run a rule for a period and create journal lines for review.

Review and Post the Reallocation Journal

Learn how to review, adjust and post the journal lines that a run created.

Manage Reallocation Runs

Learn how to follow up on runs, open their journal lines, and delete runs that are not posted.

2.1 - Create Reallocation Rules

Learn how to create a rule that describes the source, the destination projects and the allocation method.

A reallocation rule describes one reallocation that you repeat every period: which cost to take, which projects receive it, how the cost is split, and how the generated journal lines are posted. Create one rule for each type of shared cost, for example one for rent and one for IT. Because each rule has its own project tasks, G/L accounts and line types, two rules can post their costs in different ways.

To create a reallocation rule

  1. Choose the ๐Ÿ”Ž icon, enter Reallocation Rules, and then choose the related link.
  2. Choose New.
  3. On the General FastTab, fill in the following fields:
    • Code - A unique code for the rule, for example RENT.
    • Description - A description of the rule. The description is copied to every journal line that the rule creates, so make it meaningful to the people who review project costs.
  4. Fill in the fields on the Source FastTab. For more information, see Source.
  5. Fill in the fields on the Destination FastTab. For more information, see Destination.

Source

The Source FastTab describes where the cost comes from and, when the source is a project, how the cost is moved off the source project.

  • Source Type - GL Account or Project. For more information, see Reallocation Sources.
  • Source Filter - Choose the Assist Edit button, and then set a filter on the G/L accounts or projects that hold the cost.
  • Reversal G/L Account No. - The G/L account on the source reversal lines. Required when the Source Type is Project.
  • Reversal Project Task No. - The project task, on every source project, that receives the reversing entry. The task must exist and be a Posting task on every project that the Source Filter matches. Required when the Source Type is Project.
  • Source Line Type - The Line Type on the source reversal lines: Budget, Billable or Both Budget and Billable. Required when the Source Type is Project.

The Reversal Project Task No. and Source Line Type fields can be edited only when the Source Type is Project. When the source is a G/L account, the run creates no reversal lines.

Destination

The Destination FastTab describes which projects receive the cost, how it is split, and how the generated lines are posted.

  • Destination Project Filter - Choose the Assist Edit button, and then set a filter on the projects that receive the cost.
  • Destination Project Task No. - The project task, on every destination project, that receives the allocated cost. The task must exist and be a Posting task on every project that the Destination Project Filter matches.
  • Destination G/L Account No. - The G/L account on the generated lines. The account must be a Posting account, must not be blocked, and must have Direct Posting selected.
  • Destination Line Type - The Line Type on the generated lines: Budget, Billable or Both Budget and Billable.
  • Allocation Method - Cost Based or Hours Based. For more information, see Allocation Methods.
  • Journal Template Name and Journal Batch Name - The project journal batch that Run Rule suggests for this rule. You can choose a different batch when you run the rule.

Filters are stored as filters, not as fixed lists. A new project that matches the Destination Project Filter is included automatically the next time you run the rule.

When you change the Journal Template Name, the Journal Batch Name is cleared. Select a batch that belongs to the new template.

Check what a filter matches

Before you run a rule, check that the filters match the records you expect. On the rule, choose one of the following actions:

  • Source - Opens the G/L accounts or projects that the Source Filter matches.
  • Destination Projects - Opens the projects that the Destination Project Filter matches.

Block a rule

To stop a rule from being run without deleting it, select the Blocked field on the General FastTab. A blocked rule cannot be run.

Delete a rule

You can delete a rule only when it has no open runs. If the rule has runs with the status Open, post or delete those runs first. For more information, see Manage Reallocation Runs.

2.2 - Reallocation Sources

Learn how to reallocate costs from G/L accounts or from other projects.

The source of a reallocation rule is where the cost to reallocate comes from. The Source Type field on the rule decides how the app finds the source total for a period, and whether it moves the cost off the source.

When to use it

Use GL Account when:

  • The shared cost is posted to the general ledger only, for example rent, utilities or insurance invoices posted to expense accounts.
  • You want to charge projects with a share of a cost that never belonged to a project.

Use Project when:

  • You collect shared costs on an overhead or shared service project, for example a central engineering team that records its time and expenses on one internal project.
  • The cost must be moved, not copied, so that the overhead project ends the period at zero.

G/L account source

When the Source Type is GL Account, the source total is the net amount posted to the G/L accounts that match the Source Filter, with a posting date in the period.

  • Debits and credits are netted. If the net amount for the period is zero or negative, there is nothing to reallocate, and the run creates no journal lines.
  • The run creates journal lines for the destination projects only. It does not create any lines for the G/L accounts.

Project source

When the Source Type is Project, the source total is the usage cost (Total Cost (LCY) on usage entries) posted to the projects that match the Source Filter, with a posting date in the period.

  • Each source project counts only when its usage cost for the period is positive. A project with no cost, or a net credit, adds nothing.
  • For each source project that contributes, the run creates a source reversal line. The line posts the project’s period cost back out with a negative quantity, to the Reversal Project Task No. and Reversal G/L Account No. on the rule.
  • The destination lines and the source reversal lines are written to the same journal batch, with the same document number, and are posted together.

After posting, the cost has moved from the source projects to the destination projects. The total cost across all projects does not change.

2.3 - Allocation Methods

Learn how the cost-based and hours-based methods split the cost between projects.

The allocation method decides how the source total is split between the destination projects. Each project’s share is based on that project’s own activity in the same period, so busy projects carry more of the shared cost than quiet ones.

Set the method in the Allocation Method field on the Destination FastTab of the rule. A rule must have a method before it can be run.

When to use it

Use Cost Based when:

  • The shared cost grows with the overall volume of project spending, for example procurement, finance or general administration.
  • Your projects are mostly material- or subcontractor-driven, and hours are not a good measure of activity.

Use Hours Based when:

  • The shared cost grows with the number of people working, for example office space, IT equipment or HR.
  • Your projects are mostly labour-driven, and you post resource time to them.

Cost Based

Each destination project’s share is in proportion to its own usage cost in the period.

  • The basis is the Total Cost (LCY) of usage entries posted to the project, with a posting date in the period.
  • Projects with no positive usage cost in the period get no share, and no journal line.
  • If none of the destination projects have usage cost in the period, the run creates no journal lines and tells you that there is no cost basis.

Formula

Project share = Source total ร— Project usage cost รท Total usage cost of all destination projects

Example

The source total is 10,000.00.

ProjectUsage cost in the periodCalculationShare
A30,000.0010,000.00 ร— 30,000.00 รท 40,000.007,500.00
B10,000.0010,000.00 ร— 10,000.00 รท 40,000.002,500.00
C0.00No usage cost, so no share-
Total40,000.0010,000.00

Hours Based

Each destination project’s share is in proportion to the resource hours posted to it in the period.

  • The basis is the Quantity of usage entries of type Resource posted to the project, with a posting date in the period.
  • Projects with no resource hours in the period get no share, and no journal line.
  • If none of the destination projects have resource hours in the period, the run creates no journal lines and tells you that there is no hours basis.

Formula

Project share = Source total ร— Project resource hours รท Total resource hours of all destination projects

Example

The source total is 6,000.00.

ProjectResource hours in the periodCalculationShare
A1206,000.00 ร— 120 รท 2003,600.00
B606,000.00 ร— 60 รท 2001,800.00
C206,000.00 ร— 20 รท 200600.00
Total2006,000.00

Rounding

Each share is rounded to the Amount Rounding Precision in General Ledger Setup. Any rounding difference is added to the project with the largest basis, so that the shares always add up exactly to the source total. If two or more projects share the largest basis, the difference goes to the one with the lowest project number.

Formula

Rounding difference = Source total โˆ’ Sum of all rounded shares
Share of the project with the largest basis = Its rounded share + Rounding difference

Example

The source total is 1,000.00, and three projects each have 10 resource hours.

ProjectHoursCalculated shareRounded shareFinal share
A10333.3333…333.33333.34
B10333.3333…333.33333.33
C10333.3333…333.33333.33
Total30999.991,000.00

The rounding difference is 1,000.00 โˆ’ 999.99 = 0.01. All three projects have the same number of hours, so the difference goes to project A, which has the lowest project number.

2.4 - Run a Reallocation Rule

Learn how to run a rule for a period and create journal lines for review.

When you run a rule, the app calculates the source total for a period, splits it across the destination projects, and writes the result to a project journal batch as journal lines. Running a rule does not post anything. You review and post the lines in a separate step.

To run a rule

  1. Choose the ๐Ÿ”Ž icon, enter Reallocation Rules, and then choose the related link.
  2. Select the rule, and then choose the Run Rule action. You can also choose Run Rule on the rule card.
  3. On the Run Reallocation page, fill in the following fields:
    • Period Start Date and Period End Date - The period to reallocate costs for. The app reads source amounts and allocation basis from entries posted in this period.
    • Posting Date - The posting date on the generated journal lines.
    • Journal Template Name and Journal Batch Name - The project journal batch that receives the lines.
  4. Choose OK.

The template and batch are filled in from the rule. If the rule has no batch, the batch you used last time is suggested. The dates are always empty, so that you do not run a rule for the wrong period by accident.

The app checks the rule, creates a reallocation run, and creates the journal lines. When it is done, it shows how many lines were created and asks if you want to open the journal.

What the generated lines contain

Each destination project gets one journal line:

  • Project No. - The destination project.
  • Project Task No. - The Destination Project Task No. from the rule.
  • Type and No. - G/L Account and the Destination G/L Account No. from the rule.
  • Quantity - 1.
  • Unit Cost (LCY) and Total Cost (LCY) - The project’s share.
  • Line Type - The Destination Line Type from the rule.
  • Description - The rule Description.
  • Document No. - The next number from the batch No. Series. All lines from the same run share the same number.

When the source type is Project, each source project also gets a source reversal line with a quantity of -1. For more information, see Reallocation Sources.

When a run creates no lines

A run creates no journal lines when there is nothing to allocate, for example when the source total for the period is zero, or when none of the destination projects have cost or hours in the period. The app tells you why. The run is still recorded, with its Source Total Amount, so you can see that the rule was run for the period.

Run a rule again for the same period

  • If the rule already has an open run for the same period, you cannot run it again. Post or delete the open run first. This protects you from allocating the same cost twice.
  • If the rule already has a posted run for the same period, the app asks you to confirm before it runs the rule again. Run it again only if you know that the period has new costs to reallocate.

2.5 - Review and Post the Reallocation Journal

Learn how to review, adjust and post the journal lines that a run created.

The journal lines that a run creates are ordinary project journal lines. You review them in the Project Journals page and post them with the standard Post action. Until you post, you stay in control: you can check the numbers, correct a share, or delete the run and start over.

To open the journal for a run

Do one of the following:

  • After a run, choose Yes when the app asks if you want to open the journal.
  • Choose the ๐Ÿ”Ž icon, enter Reallocation Runs, and then choose the related link. Select the run, and then choose Open Journal.

The journal opens on the run’s batch, filtered to the lines of that run.

Review the lines

The following fields on the journal lines show where a line came from. You can add them to the page with Personalize if they are not shown.

  • Reallocation Run No. - The run that created the line. Blank on lines that you entered yourself.
  • Reallocation Line Type - Destination for a line that brings cost to a project, or Source Reversal for a line that moves cost off a source project.
  • Reallocation System Amount - The amount that the run calculated for the line.
  • Reallocation Adjusted - Selected when someone changed the quantity or cost on the line after the run created it.

Adjust a destination line

You can change the quantity or cost on a destination line, for example to move part of a share from one project to another. When the total cost of a line changes, the Reallocation Adjusted field is selected. The Reallocation System Amount keeps the amount that the run calculated, so you can always see the original value.

You can also change the No. field to post a line to a different G/L account. The quantity and cost on the line are kept.

To post the journal

  1. In the Project Journals page, check the lines.
  2. Choose Post.

Before anything is posted, the app checks every run in the batch. The destination lines of a run must add up exactly to the amount the run needs to allocate:

  • For a G/L account source, the destination lines must add up to the run’s Source Total Amount.
  • For a project source, the destination lines must add up to the total of the source reversal lines.

If a run does not add up, for example because you changed or deleted a destination line, posting stops before any line in the batch is posted. The message names the run, the current total and the amount it must add up to. Adjust the destination lines and post again.

Result

  • The app creates Project Ledger Entries for the lines, through the standard project journal posting.
  • Each project ledger entry keeps the run number, the line type, the calculated amount and the adjusted flag from its journal line. For more information, see Trace an Allocation Back to its Source.
  • When all of a run’s lines are posted, the run status changes from Open to Posted.

2.6 - Manage Reallocation Runs

Learn how to follow up on runs, open their journal lines, and delete runs that are not posted.

Every time you run a rule, the app records a reallocation run. The run keeps the period, the posting date, the source total and the journal batch, and a copy of the rule’s source filter, destination filter and allocation method as they were at the time of the run. Later changes to the rule do not change the history.

To view reallocation runs

Do one of the following:

  • Choose the ๐Ÿ”Ž icon, enter Reallocation Runs, and then choose the related link.
  • On a reallocation rule, choose the Runs action to see the runs for that rule only.

For each run, you can see the following:

  • Entry No. - The run number. The same number is on every journal line and ledger entry that the run created.
  • Rule Code - The rule that was run.
  • Period Start Date and Period End Date - The period the run allocated costs for.
  • Posting Date - The posting date on the generated journal lines.
  • Source Total Amount - The total cost that the run found to allocate.
  • Status - Whether the run’s lines are posted.

Status

  • Open - The run has journal lines that are not posted yet.
  • Posted - All of the run’s journal lines are posted.

Actions on a run

  • Open Journal - Opens the project journal on the run’s batch, filtered to the run’s lines. Available for open runs.
  • Delete - Deletes the run and all the journal lines it created. Available for open runs.
  • Posted Entries - Opens the Project Ledger Entries that the run created. Available for posted runs.

To delete an open run

Delete a run when the result is wrong and you want to start over, for example when the rule had the wrong filter, or costs were posted to the period after you ran the rule.

  1. Choose the ๐Ÿ”Ž icon, enter Reallocation Runs, and then choose the related link.
  2. Select the open run.
  3. Choose Delete.
  4. Confirm that you want to delete the run and its generated journal lines.

The app deletes the run and all of its journal lines, including source reversal lines. Journal lines that you entered yourself in the same batch are not affected. You can then correct the rule and run it again for the same period.

3 - Trace Reallocated Costs

Learn how to trace a posted project entry back to the run and rule that created it.

Reallocated costs are only useful when people trust them. A project manager who sees an overhead charge on their project wants to know where it came from and how it was calculated. An auditor wants to see that a posted amount matches what the rule calculated, or who changed it.

Pryme Cost Reallocation keeps this link for every posted entry. Each Project Ledger Entry that a run created carries the run number, and from the run you can get to the rule, the period and the source filter.


Trace an Allocation Back to its Source

Learn how to see the run, rule and calculated amount behind a posted project entry.

3.1 - Trace an Allocation Back to its Source

Learn how to see the run, rule and calculated amount behind a posted project entry.

The Reallocation Trace FactBox on the Project Ledger Entries page shows whether a posted entry was created by a reallocation run, and how. You do not need to leave the page or search for the run.

To trace a posted entry

  1. Choose the ๐Ÿ”Ž icon, enter Projects, and then choose the related link.
  2. Select a project, and then choose Ledger Entries.
  3. Select an entry.
  4. In the FactBox pane, look at the Reallocation Trace FactBox.

The FactBox shows the following for an entry that a run created:

  • Reallocation Run No. - The run that created the entry. Choose the value to open the run.
  • Rule Code - The rule that was run. Choose the value to open the rule.
  • Period Start Date and Period End Date - The period that the run allocated costs for.
  • Reallocation Line Type - Destination for cost brought to the project, or Source Reversal for cost moved off the project.
  • Reallocation System Amount - The amount that the run calculated.
  • Reallocation Adjusted - Selected when someone changed the amount on the journal line before it was posted.

For any other entry, the FactBox shows This entry was not generated by a Cost Reallocation run.

Find all entries from a run

To go the other way, from a run to all of its posted entries:

  1. Choose the ๐Ÿ”Ž icon, enter Reallocation Runs, and then choose the related link.
  2. Select a posted run.
  3. Choose Posted Entries.

The Project Ledger Entries page opens, filtered to the entries that the run created, on all destination and source projects.

4 - Pryme Cost Reallocation Release Notes

15.0 (November 2026)

Required BC version: 28.0

First version of Pryme Cost Reallocation. The app spreads shared costs, such as rent, IT or a shared service project, across the projects that benefited from them, so that every project carries its fair share of overhead. You define a reallocation rule once, with a source of G/L accounts or projects, a set of destination projects, and an allocation method based on cost or hours. Each period, you run the rule for a date range, and the app writes each project’s share to a project journal for you to review, adjust and post. Every posted project ledger entry keeps a link to the run and rule that created it, so allocated costs can always be traced back to their source. Learn more about Pryme Cost Reallocation here.